The Upper Lake Union High School District’s facilities needed more than just modernization.
Aspen Street Architects, working with the District, was able to support funding and then design the replacement of almost the entire campus. In all, the work included the replacement of a modular campus with permanent offices, classrooms, library, multipurpose/food service and lab buildings along with the modernization of the remaining campus.
The project was complicated by a difficult contractor, a phased long term master plan and changes in school administration. The final phase of construction was completed in 2008 with the installation of a modular music room, and a shade structure. The result of all this work is a beautiful and functional campus, built on budget and on time.